Projects from HQrs/RO

 

PROJECTS GIVEN BY HQ / RO

A/R & M/O:

Ø  The A/R & M/O work of colouring white Washing and Painting work is taken up for Staff Quarters & academic block inside during 2017-18.

 

The following special M&R works sanctioned & work completed.

1) The Barbed wire fencing work over the existing compound wall has been completed by CPWD, Goa for Rs. 5,00,000/- (Sanctioned by NVS, RO, Pune & Work is completed) and work completion report is submitted in March 2015 to NVS, RO, Pune.

2) Special Repair work of replacement of burnt cables and switches has been completed by CPWD (Elect.), Pune for the amount of Rs. 4,98,000/-. (Sanctioned by NVS, RO, Pune & Work is completed in the month of July 2015).

3) Providing street light near staff quarter and girls dormitory and high mast pole for security purpose estimate was submitted by CPWD (Elect.), Pune for Rs. 5,88,000/- has been forwarded to NVS, RO, Pune for A/A & E/S for the amounts of Rs. 5,88,000/- on 26.11.2014 & sanction was received only for an amount of Rs, 5,00,000/-. The same amount has been deposited on 27.06.2015 to CPWD (Elect.), Pune by the vidyalaya. The work is completed on 31.03.2016 & settlement is made on 28.07.2016.

4) Providing street lights near staff quarters and new dormitory including safety lights IETC at JNV Palus, Dist. Sangli (Part II) has been forwarded to NVS, RO, Pune for A/A & E/S for the amount of Rs. 2,90,000/- on 07.10.2015 & sanction is received of Rs. 2,90,000/- & vidyalaya has forwarded the cheque drawn in favour of  Executive Engineer (Electrical), PCED, CPWD, Pune on 18.11.2015. Work is completed on 31.03.2016 & settlement is made on 28.07.2016.

5) Rs. 5,25,000/- sanctioned by NVS, RO, Pune vide letter no. F.8-45(PHS)/Sanction /NVS(PR) /2016-17/4390, dated 13.01.2017 for construction of Ramps / Slopes and toilets for Physically handicapped students at JNV Palus, Dist. Sangli (MS) & vidyalaya has forwarded the demand draft drawn in favour of  The Executive Engineer, CPWD, Goa on 25.01.2017.

 

 

Estimate sanctioned have been forwarded to NVS (RO) Pune & NVS, Hqrs, Noida & A/A and E/S pending:

1) Estimates for Rs. 7,35,000/- for fixing the Study table in the dormitories has been taken from CPWD, Goa and is forwarded to NVS, RO, Pune on 15.01.2014 for A/A & E/S.

2) Estimates for Rs. 22,70,800/- & Rs. 48,19,600/- for fixing of wire mesh shutters to door & windows to prevent mosquitoes entry in the buildings i.e. in 05 dormitories and 16 Nos. of Type III staff quarters and 06 Nos. of Type I quarters has been taken from CPWD, Goa and forwarded to NVS, RO, Pune on 04.06.2014 for A/A & E/S.

3) Estimate for approach road for newly constructed dormitory has been submitted by CPWD, Goa & same has been forwarded to NVS, RO, Pune for A/A & E/S on dated 24.01.2015 an amount of Rs. 4,20,200/-.

 

ESTIMATE SUBMITTED FOR A/A & E/S RECEIVED FROM CPWD (ELEC.), PUNE.

1)    Estimates for Rs. 9,42,195/- for Replacement of conventional street light fittings with energy efficient LED fittings at JNV Palus, Dist. Sangli.

2)    Estimates for Rs. 22,66,176/- for Renovation of IEI & Fans of Staff quarter at JNV Palus, Dist. Sangli.

3)    Estimates for 2,25,402/ - for Special repair of DP structure along with switch gears at JNV Palus, Dist. Sangli.